Dhaka Tangail Highway Street Views by bike on October 2020



Dhaka Tangail Highway Street Views:
Name of the Project: 
SASEC Road Connectivity Project: Improvement of Joydevpur ChandraTangail-Elenga Road (N-4) to a 4-lane Highway.
Name of the Project : 
SASEC Road Connectivity Project: Improvement of Joydevpur Chandra-Tangail-Elenga Road (N-4) to a 4-lane Highway. Project Director’s Information Name: Md. Ishaque
ID No. 006002
Project Director (ACE, CC), RHD
Phone: 8802-9859117 Mobile: 01713-176477

Location of the Project Dhaka, Gazipur and Tangail:

Objectives of the Project Upgrading of existing 70 km Joydevpur-Chandra-Tangail-Elenga (JCTE) 2 Lane Road to 4 Lane Highway Construction of 11 Flyovers/Overpass, 53 Bridges and 76 Culverts, Construction of separate lane for slow moving vehicles along the JCTE Road
Identification of accident prone locations along JCTE Road and improvement in line
with road safety, Construction of RHD Headquarters Building at Tejgaon, Dhaka
Main components of the Projects
a) Length of the Road 70km
b) Bridges 53
c) Flyover 9
d) Railway Overpass 2
e) Steel Foot over bridges 6
f) Box Culvert 76

Project Duration Approved Expected:

April 2013 To June 2020 April 2013 To June 2020
Project Approval Status Approval Status Cost Duration
Total GoB PA
Original 278845.55 Lac 94477.34 184368.21 April 2013- March 2018
1st Revised 306680.23 Lac 122312.02 184368.21 April 2013- March 2018
Special Revised 336474.95 Lac 152106.74 184368.21 April 2013- March 2018
2nd Revised 559315.88 Lac 217253.02 342062.86 April 2013- June 2020
Others Source of Fund Asian Development Bank (ADB), OPEC Fund for International Development (OFID) and Abu Dhabi Fund for Development (ADFD) Year Wise Financial
Information Year DPP cost Phasing 
(lac BDT)
ADP/RADP
Allocation
(Lac BDT)
Expenditure
(lac BDT)
2012-13 - - -
2013-14 17821.13 17821.00 17820.94
2014-15 15703.45 15755.60 15703.45
2015-16 112724.30 59000.00 58999.98
2016-17 111990.37 62016.00 62015.982
2017-18 78235.70 87000.00 86977.59
2018-19 159486.48 105,000.00 105,000.00
2019-20 107038.66 75,000.00 38,105.90

Present Progress (384,623.59 Lac till February 2020)
Major Components Quantity & Unit Progress (%) Financial (%)
a) Length of the Road 70km 4-lane Highway Physical work of 70 km road widening, construction of 26 Bridges, 3 Flyovers, 2 Railway Overpass and 60 Box culverts is in progress.
Physical progress of project 75.48%. 68.77%
b) Bridges 53
c) Flyover 9
d) Railway Overpass 2
e) Steel foot over bridges 6
f) Box Culvert 76

Travel Route:  
kazipara, mirpur 10, mirpur 2, mirpur 01, Technical, Gabtoli, Aminbazar, saver, ashulia, EZP, Chandra, mirzapur, tangail, alenga,  sirajganj jamuna bridge